Visualization of S-CAP's data-driven submarine cable protection design with variable burial depths and protective structures
Gochang, South Korea, September 3, 2025
Korea Electric Power Corporation has introduced S-CAP, a data-driven software tool that standardizes submarine cable protection by quantifying risk, recommending optimized protection measures and producing design reports. S-CAP accepts site-specific inputs such as anchor types, wave and current conditions, and detailed seabed properties to calculate variable burial depths and recommend alternatives like rock berms or concrete ducts. Backed by numerical modelling and full-scale tests at a large Korean testing centre, the program has received formal document verification and has been applied to a major offshore wind grid link, delivering improved transparency, lower repair risk and cost savings.
The development of data-driven protection for submarine cables is advancing as part of efforts to accelerate the energy transition and cross-border power interconnections. Submarine cables remain critical links between offshore generators and onshore demand centers, and recent incidents have underscored the high costs of restoration and the importance of safeguarding cables to maintain reliable power supply and avoid widespread outages. Protection strategies must account for marine environment factors such as anchors, currents, wave energy and seabed conditions, making standardized engineering practices a priority for international grid reliability.
KEPCO Submarine Cable Protector (S‑CAP) is computer software that offers scientifically quantified and optimized protection options for submarine cables. It embeds a set of standards developed to shield cables from a range of marine environmental risks. The software transforms protection from a reactive task into a proactive, data-driven design process. Users input environmental and engineering variables such as anchor types and weights, wave height, current velocity and seabed properties (including unit weight, undrained shear strength and internal friction angle). The program then automatically calculates burial depth for each route segment, proposes multiple protection schemes, and recommends the most appropriate option. It also generates cross-sectional drawings and a comprehensive design report.
The system standardizes and streamlines the protection design process, reducing subjectivity and improving documentation and traceability. KEPCO converted empirical observations into engineering standards and developed chart-based design tools for estimating burial depth under varying anchor types and seabed conditions. It also codified quantified standards for protective structures such as rock berms, including dimensions, materials and installation tolerances, with S‑CAP operating on burial or protective structures as required. By applying variable burial depths tied to localized risk, S‑CAP aims to be more effective and economical than uniform-depth methods.
Extensive numerical simulations and full-scale validation tests were conducted at a dedicated testing center with expansive facilities for transmission lines and underground cables, enabling trials under realistic conditions. A key design principle established from testing is that burial depth should exceed the sum of maximum anchor penetration and a safety margin. This empirical finding was converted into formal engineering standards to guide practice.
Validation progressed with formal recognition in February 2024, when a document verification was issued by a global classification and certification body. The verification highlighted the method as scientifically rigorous, quantitatively based and applicable to real-world submarine cable protection projects. The software is positioned to support global projects across offshore wind connections, HVDC transmission corridors and interregional energy links, and it is applicable to both HVDC and AC submarine cables. In practical terms, the method is expected to reduce construction costs by around 5%, roughly USD 2 million per 100 kilometers of cable, according to the cited estimates.
The software was applied to a major wind-to-land connection project along the Korean southwest coast, with grid integration targeted by 2029 and full completion by 2031. Deployment of S‑CAP on this project led to a reduction of cable installation costs by an estimated 50%, about USD 3.6 million, while also reducing environmental impact. The digitized reporting format and transparent design logic helped strengthen trust between project owners and contractors, illustrating how data-driven methods can support collaboration and accountability in complex offshore builds.
Preventing cable damage before it occurs strengthens structural integrity and durability of submarine conduits, reducing the risk of outages and costly repairs. A standardized, data-driven design method supports stable electricity transmission to vulnerable or remote regions, including island communities, in high-risk environments. The approach integrates field-tested methodologies with globally recognized design principles to deliver a holistic protection strategy.
A consortium is pursuing a turnkey undersea telecommunications link of about 260 km between Busan, South Korea, and Fukuoka, Japan. The Busan–Fukuoka project is set to be completed by 2027 and is described as LS Cable & System’s first international submarine cable contract of this scale. The JAKO cable will strengthen connectivity to support mounting demands of AI workloads and cloud services in Northeast Asia, aiming to accommodate rising data traffic driven by major cloud providers. LS Cable & System, established in 1962, is a global manufacturer offering design, engineering and installation services for HVDC systems, renewable-energy cables and submarine telecom cables, and it plans to oversee the full EPC process to deliver a future-proof link between the two nations. The JAKO cable is positioned as a strategic response to growing regional infrastructure needs amid expanding economic and geopolitical ties across Asia.
Construction has begun on a new subsea cable connecting East Asia and the United States. The E2A cable is planned to run about 12,500 km and will land at Toucheng in Taiwan, Busan in South Korea, Maruyama in Japan and Morro Bay, California. Built by a major subsea systems supplier, the E2A line will support more than 192 terabits per second across 12 fiber pairs and will employ 18 kV power technology. The project is set to go live in the second half of 2028. The consortium includes SoftBank, SK Broadband, Chunghwa Telecom and Verizon, with SoftBank providing the Maruyama landing station. In the broader context, other recent initiatives include plans to invest in subsea routes between the US and Japan, illustrating growing momentum for robust, cross‑regional data infrastructure to support AI, cloud and digital services. The E2A project is designed to complement other cables linking the US West Coast to Northeast Asia, reflecting a broader push to diversify routes and capacity across the Pacific corridor.
These developments reflect a trend toward formalizing submarine cable protection through standards, validated methods and transparent reporting. They also highlight the evolving role of cable systems in supporting high-capacity, low-latency connectivity for offshore energy integrations, AI workloads and global data flows.
The KEPCO Submarine Cable Protector is a software tool that provides quantified, standardized design options for protecting submarine cables. It integrates environmental inputs, generates burial depths, suggests protection schemes, and outputs design reports to support a data‑driven approach to cable protection.
Users input environmental and engineering variables such as anchor types and weights, wave height, current velocity and seabed properties. The software then calculates optimal burial depth for each route segment, offers multiple protection options, and produces design drawings and a comprehensive report.
Benefits include standardized design practices, reduced subjectivity, improved documentation, potential cost reductions, and better alignment of burial and protective structures with localized marine risk profiles.
It is applicable to both HVDC and alternating-current submarine cable projects and is intended for offshore wind connections, HVDC transmission corridors and interregional energy links.
Related initiatives include a Busan–Fukuoka undersea telecom link being developed on a turnkey basis and the E2A subsea cable connecting East Asia with the United States, featuring high capacity and multi‑landing points.
Feature | Description |
---|---|
Subject | Advances in submarine cable protection design and its application to major offshore and interregional cable projects |
Software | S‑CAP provides quantified burial depths, multiple protection options and documentation outputs based on localized marine risk data |
Standards and validation | Engineering standards embedded in the tool; formal verification by a major certification body in 2024; applicable to HVDC and AC systems |
Key outputs | Optimal burial depths, protection recommendations (burial, rock berms, etc.), cross‑sectional drawings and design reports |
Supported projects | South Korea’s offshore wind connections, Busan–Fukuoka undersea link, JAKO telecom cable, and East Asia–U.S. E2A cable |
Cost and risk impact | Potential reductions in installation costs and environmental impact; improved reliability and project transparency |
Villa Rica, September 5, 2025 News Summary Villa Rica-based Caliber 1 Construction is expanding its Building…
New York, September 5, 2025 News Summary Pave Finance closed a $14 million seed round that…
Spain, September 5, 2025 News Summary Tini Living is shipping factory-built prefab homes from Spain to…
Northeast, U.S., September 5, 2025 News Summary Construction firms are being urged to accelerate adoption of…
Illinois, September 4, 2025 News Summary Aspen Power has acquired two community solar projects in Illinois…
Illinois, September 4, 2025 News Summary Illinois juvenile facilities are implementing expanded vocational training programs to…